Capital Project Update
The capital project continues to make good progress. The high school locker room and athletic offices demolition is nearly complete. This area will house the new pool. During the week of April 10, construction of the footers for the new foundation will start.
The former Agriculture classroom and woodshop demolition is nearing completion. This area will become the new locker rooms and athletic offices. During the week of April 10, the concrete floor in this area will be removed to allow for plumbing lines to be installed.
The former soccer field has been stripped of the topsoil. Gravel and crushed stone are being put in place along with drainage tile for the new parking lot.
The area for the new multi-purpose, artificial turf athletic field is being cleared of topsoil.


COMMUNITY FORUM DATES:
Wednesday, January 11, 2023
at 6:30 p.m. in the Hugh C. Williams Senior High School Library
Wednesday, February 1, 2023
at 6:30 p.m. in the Hugh C. Williams Senior High School Library